Does my new outbuilding need building regulations approval?

Blog Post
workshop building regulations

With the increase in people working from home during the pandemic, it seems a useful time to revisit the topic of building regulations and small detached buildings, especially those that are to be constructed in domestic settings as home offices, workshops and other uses.

As a rule, the construction of any new building is likely to be work that is controlled under the building regulations. However, there might be cases where some small, detached buildings can be treated as exempt from them. Previous LABC articles have touched on exempt or garden buildings, but here we’ll discuss small detached buildings in a little more depth.

Under the building regulations the erection of a building is treated as controlled building work – to which the building regulations must be applied and for which a notice must be given to the local authority before the work begins.

However, building regulation 9 allows some exceptions. These exceptions – or exemptions – can be found in Schedule 2 of the regulations.

The circumstances that permit three types of small, detached buildings to be exempt from the building regulations can be found in Class 6 of the Schedule (one of these is an air-raid shelter!). 

This article focuses only on the following Classes of exempt small, detached buildings:

  • Those with a floor area not exceeding 30m2; and
  • Those with a floor area not exceeding 15m2

To be exempt from the regulations they must have the features listed below and they must not contain any sleeping accommodation (no beds in sheds).

Small, detached buildings less than or equal to 30m2

These must be single storey – a roof mezzanine or loft floor would not be permitted, and:

  • The internal floor area must not be greater than 30m2 (for example 3m x 10m, or 5m x 6m), and
  • The building must be constructed substantially of non-combustible material unless it is 1m or more away from any boundary.

These types of buildings are typically used as garages, workshops, home offices, garden rooms, saunas, solariums, indoor pools.

The boundary measurement rule is important as features such as fascias, soffits, guttering, rainwater pipes - anything that is part of and protrudes from the building - can be counted as being a point from which the closeness to the boundary can be measured. If any part of the building is between 0m to 0.999m then the materials that can be used for construction must be controlled.

In the case of a building closer than 1m to the boundary – to retain the exemption status – materials must be, in the main, non-combustible. That means they should be, for example, walls of brick, block, concrete panel, steel frame with metal cladding etc, and roofs of slate, clay or concrete tiles, or metal cladding.

If the building is 1m or more away from the boundary there are no restrictions on the type of materials that can be used.

Small, detached buildings less than or equal to 15m2

These are not limited to being single storey.

  • The internal floor area must not be more than 15m2 (for example 3m x 5m, or 2-storeys of 7.5m2 each).
  • There are no restrictions in relation to the closeness to the boundary, or the type of materials that must be used.

These smaller buildings can be constructed anywhere within the boundaries of the site (in the garden of a house, for example) and can be constructed from any material – for example it can be a wooden shed, gazebo, sauna, log-cabin, or fabric tent, or plastic playhouse etc.

It's important to know that the 'floor area' of the building means the aggregate area of every floor in the building, calculated by reference to the finished internal faces of the walls enclosing the area, or if at any point where there is no wall, by reference to the outermost edge of the floor. For example, in the case of a garage, if part of one wall is made up of a garage door, the measurement would be to the outside edge of the floor slab.

If the physical features or use do not fit with the rules for exempt status, this does not mean that the building can't be built, it just means that the work is controlled and must be notified to the council under the building regulations, and that a Full Plans or Building Notice application must be made, and the work must be inspected. (Visit the LABC Front Door website for information on how to apply for building regulations approval.) 

Queries can also be discussed with your local authority building control team before you make an application - you can find their direct contact details using the LABC postcode search above.

If the detached building can be treated as exempt then other features can be classed as being exempt too – such as the provision of any toilets, showers, boilers or wood-burning stoves etc. inside the building, so long as these features do not materially change the status of the exemption.

To clarify how this work is controlled:

  • The installation of any electrics where the electricity is from a source shared with or located inside a dwelling, in which case the installation must comply with Part P of the regulations and is notifiable work through a competent persons scheme. 
  • The installation of cold or hot water supplies from a source shared with or located inside any building other than a building or extension of a kind also described in Schedule 2, in which case the work must comply with Parts G1 – Cold water supplies and G3(2) & (3) Hot water storage systems of the building regulations -  and is notifiable work.
  • The extension of any existing drainage system to serve the exempt detached building, in which case the extended drainage must comply with Parts H1 – Foul drains; H2 – Wastewater treatment and cesspools; H3 – Rainwater drainage, where applicable however the drainage is part of the exemption and so doesn't have to be notified to the local authority.
  • Whether a building can be treated as fully exempt from the building regulations or not, there are other matters that must also be considered and/or addressed before any work begins.
  • Will the building require planning permission? (External link to the LABC Front Door website for further information.)
  • Will a building over agreement (BOA) be required from the sewer authority – in the case of the building being constructed on or close to a public sewer?
  • Will permission be required from the gas, electricity, or water authorities for building over or close to any pipes or cables?

Ignoring the above, regardless of building regulations, could result in a fine and/or the building being removed. Similarly, exemption from building regulations does not mean that the building should be unsafe and advice from a qualified and competent construction professional should always be obtained before embarking on such a project, to ensure the building is both safe and compliant. (Read the Front Door advice on choosing and working with a builder.)

Finally, where an existing exempt building is added to, by an extension, and the floor area increases to a point that the building is no longer exempt, this would be treated as a material change of use and the building regulations would apply to both the extended part and the existing building, and the work would be controlled and notifiable.

Further information

Building Regulations Part H (England): Drainage and Waste Disposal

Building Regulations Part H (Wales): Drainage and Waste Disposal

 


Please Note: Every care was taken to ensure the information was correct at the time of publication. Any written guidance provided does not replace the user’s professional judgement. It is the responsibility of the dutyholder or person carrying out the work to ensure compliance with relevant building regulations or applicable technical standards.

This article was reviewed and updated on 10 August 2023

Comments

Small detached exempt buildings

Submitted 3 years 9 months ago

So... we need a HETAS certificate in the home, but we can installed a solid fuel burner in an except building without building regulation control, has this not been though through or is it because there will be no sleeping accommodation in the exempt building?

Exempt Buildings

Submitted 3 years 9 months ago

The Planning Portal and the Building Regulation Manual indicate that all work is exempt from the Building Regulations if it falls under the criteria for an exempt building under Schedule 2 except AD P

Change of guidance

Submitted 3 years 9 months ago

Good morning,
Could you please clarify why the guidance for exempt buildings has now changed from the previous guidance issued in your 'Viewpoint' document some years ago? This suggested home offices were exempt, apart from needing to comply with Regulation 9 (Exempt Buildings and Work) i.e. G1, G3, and P1.

Thanks

Exempt garden buildings

Submitted 3 years 9 months ago

Can you please offer clarification that if a timber building, between 15m2 and 30m2 is proposed within 1m of the boundary, then if the boundary facing wall is made suitably fire resistant, i.e lined on both faces with appropriately fire rated boarding, and then clad externally with a fire rated cladding such as HardiePlank, that this would then be considered to be exempt?

Exempt building height

Submitted 3 years 9 months ago

Hi,
Great advice, thanks. Can you confirm the height restrictions on a less than 30 sq Mtr exempt garden building built from non combustible material but within 1m from the boundary fence.

Conversion of existing outbuilding to a non-sleeping place

Submitted 2 years 11 months ago

Hi,

My outbuilding internal floor area is of 5.3 meters width and 6.62 meters length and is used as garage and storage purpose currently. This was built over 15 years ago.
I'd like to upgrade it to a non-sleeping accommodation. If converted entirely, it will cross 30meter square which will not be exempt from control under the current Building Regulations. So, I'd like to leave a part of it for garage(25%) and upgrade (with proper insulation for walls and floor) the rest 75%, which will be under 30 meter square so that it is exempt from control under the current Building Regulations. Can you please clarify my understanding.
Thanks.

LABC response

Submitted 2 years 11 months ago

Hi,

Thank you for your enquiry regarding your proposal to convert your existing garage into non-sleeping accommodation. The existing building, is already more than 30m2 in floor area, from the dimensions you have given, and is outside the scope of being exempt under Class 6 of Schedule 2 of the Building Regulations 2010 (as amended). As such any building work that you carry out, whether or not you partition part of the building from another part, will require notification to your local authority.

We recommend that you discuss your proposal with your local authority building control team as they are the enforcing authority for the building regulations in your local area and who will be able to advise you better on your particular project.

Best,
LABC team

Attached garage

Submitted 2 years 10 months ago

Do I need permission to extend the length of my garage which half of its length is attached to the side of house. Want to extend the length that’s not attached further into my garden to give more garage / storage space

LABC response

Submitted 2 years 10 months ago

Hi,

Thank you for your enquiry regarding your proposal to extend your existing attached garage. As the garage is not a detached structure it falls outside the scope of the exemptions given under Class 6 of Schedule 2 of the Building Regulations 2010 (as amended). The extension will require notification to your local authority. We recommend that you discuss your proposal with your local authority building control team as they are the enforcing authority for the building regulations in your local area and they should be able to advise you better on your particular project.

Best,
LABC team

Open fronted hot tub shed

Submitted 2 years 9 months ago

I have a detached hot tub shed which is 3.6 x 6.7m. It has 6 posts which are taken down to pad foundations. The floor of the shed is decking suspended above ground level & the roof is decra sheets. The shed is 2.1m from the boundary fence. I have built the shed over my private drain, but have left inspection points in the decking of the shed floor. Can you please advise if this is exempt from regs & acceptable.

Add new comment

This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Sign up to the building bulletin newsletter

Over 48,000 construction professionals have already signed up for the LABC Building Bulletin.



Join them and receive useful tips, practical technical information and industry news by email once every 6 weeks.



Subscribe to the Building Bulletin