“My Dad told me about them!” Storm tanks

Blog Post
Picture of rain falling

If you’ve ever found a storm tank on site you will know how they can impact on building work.

Picture of a storm tank

They’re commonly found at the back of terraced properties and originally acted as a soakaway for rainwater drainage.

Built in brickwork they can range in size from 900mm diameter and 900mm deep to 3m diameter and 5m deep, depending on how many properties discharge into it. They had a brick vaulted roof reducing to a manhole size opening at the top. Some were even constructed internally and house owners would draw water from them to use for washing clothes. 

Most disappeared as kitchens were extended, particularly in the 1980’s, because they were so close to the building. Whilst some still remain, they’re likely to be obsolete and are filled with a variety of garden rubble, refuse and silt. Most commonly it was the rubble from the former demolished outside toilet!

The real problem arrives when looking to add an extension.

Foundations need to be taken down to ‘a suitable loadbearing strata’ and having a 2m deep storm tank on the corner of the proposed extension position can create a very expensive additional cost, both in terms of extra spoil to cart debris away and extra concrete to bring back to formation level. There’s also the cost of redirecting drains and ensuring they don’t impact on wall lines. 

Storm tanks were introduced at a time when only foul water drainage was seen as a problem. Once it was realised that having such a concentration of water near to the building could be the cause of foundation failure things changed again. 

Picture of a storm tank

In time they were replaced by combined drainage systems carrying both foul and rainwater, then separate surface water drains were introduced for new builds to move water away altogether and into water courses. This was expensive and, where ground conditions allowed, cheaper soakaways positioned at least 4.5m away from any building became commonplace.

Since 2002, Building Regulation H3 has required that rainwater is only discharged to a sewer as a last resort and only where an ‘adequate soakaway or some other adequate infiltration system is not reasonably practicable’. Even then it should be taken to a watercourse before a sewer discharge is considered.

As a result we have seen the emergence of ‘harvested rain water’ particularly in relation to water efficiency requirements for new housing. Instead of a soakaway, this solution uses sealed tanks with an overflow facility to collect the rainwater which is then used for toilet flushing and washing machines.

We’ve now seen the storm tank principle come full circle.

They knew what they were doing in them olden days, we’ve just tweaked it to work better for us today!

Found this interesting?

Browse our "My dad told me about..." articles

(Pictures courtesy of camulos.com and thecolchesterarchaeologist.co.uk)

 


Please Note: Every care was taken to ensure the information was correct at the time of publication. Any written guidance provided does not replace the user’s professional judgement. It is the responsibility of the dutyholder or person carrying out the work to ensure compliance with relevant building regulations or applicable technical standards.

This article was reviewed and updated on 10 August 2023

Comments

Add new comment

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Sign up to the building bulletin newsletter

Over 48,000 construction professionals have already signed up for the LABC Building Bulletin.

Join them and receive useful tips, practical technical information and industry news by email once every 6 weeks.

Subscribe to the Building Bulletin