Beware: Don’t just bolt your beams!

Blog Post
Builders pointing at beams in the roof

The traditional approach used when two steel beams are provided to support a cavity wall has been to design the beams to each carry half the total load and then connect them with pipe spacers and bolts, even when the loading to each beam was not equal.

This view has been challenged by many structural engineers who say you should not rely on spacers and bolts to fix them together. This becomes more important where the beams are likely to carry different loads, a typical situation in a cavity wall where the inner leaf carries the floor joists, resulting in significantly different loads on the inner and outer beams.

It is common for structural engineers to specify I-beams, also known as Universal Columns (UC), for situations described above. The horizontal elements in an I-beam are called “flanges”, and the vertical element is called the “web”.

I-beams are excellent at resisting vertical loading and bending as these are parallel to the web. However, I-beams are generally weaker in torsion, which may lead to twisting or deflection in the beam, particularly when unevenly loaded – this could result in cracking of masonry above, and in severe cases this could lead to failure of the beams.

So, steel beams and their connection details should always be designed by a competent structural engineer. Depending on the individual situation and the loadings involved, the structural engineer may specify one of several options to connect beams together and reduce torsion, such as:

 

  1. using bolts and spacers at regular centres
  2. welding the beams together or providing a continuous welded plate over the top of both beams
  3. provide web stiffeners between the flanges of each beam

Ideally, onsite welding should be minimised where possible to reduce fire safety risks. If welding is unavoidable, it should be adequately planned and carried out in a safe manner by a competent person – and remember also to check if the client has a ‘hot works permit’ approval process in place before commencing.
 

Want to read more about traditional building techniques and structures?

Take a look at our articles from the "My dad told me about them!" series. Our most popular ones include:

You might also find this article useful: Beware of point loads on beams.

 

Please Note: Every care was taken to ensure the information was correct at the time of publication. Any written guidance provided does not replace the user’s professional judgement. It is the responsibility of the dutyholder or person carrying out the work to ensure compliance with relevant building regulations or applicable technical standards.

This article was updated on 1 August 2022

Comments

In reply to by Stephen D'Aulby (not verified)

Sense

Submitted 3 years 7 months ago

Couldn't agree more!

In reply to by Stephen D'Aulby (not verified)

Beam Depth

Submitted 3 years 4 months ago

Very interesting. So do you typically provide a target midspan deflection in mm (25-50% of theoretical dead as stated) for contractor to achieve with steel wedges? Obviously relying on some contractor experience to spread this load with a series of wedges along beam length. Do you then advise dry packing at this point? Or release temporary propping and then dry pack once beam has deflected remaining dead/static load amount? Thanks in advance.

In reply to by Stephen D'Aulby (not verified)

beam deflection

Submitted 3 years 1 month ago

Excellent points here, thank you.

Depends

Submitted 5 years 7 months ago

I've used them over 5m with no deflection problems; depends which weight you use.

Pairs of beams

Submitted 5 years 7 months ago

Or design pairs of beams to have similar deflections whenever possible (say 152UC for heavily loaded inner leaf and 152UB for outer leaf).

Welded stiff plates between beams seem very excessive and difficult and time-consuming to install.

Pre-loading beams

Submitted 5 years 7 months ago

How do you all feel about the idea of pre-loading beams (thereby inducing the calculated deflection) by using folding steel wedges at the centre of the span before slating and packing under the masonry above.
Then once the acrows are removed there is no cracking ...

How we design

Submitted 5 years 7 months ago

I'm working on a couple of schemes at them moment where we've been brought in to deal with problems of deflection to the structure and finishes above.
Example: Engineer has assumed load transfer between beams by way of pairs of bolts at 750 ctrs through web with spacers/lock nuts. To me that's no better than a single and provides no load transfer without significant bending or twisting occurring. Engineer has also assumed quarter point restraint via this bolted connection!!
203UB25 spanning 5.8m = big deflection
We always design as follows:
1. Unless wall above is 215mm solid we design the worst case beam.
2. Restraints are used where we have detailed it. So if we need restraint at third points we'll detail strapping to the structure (not to the adjacent beam, this is not adequate).
3. If we do tie the beams together, to restrain both back to the structure, then we detail top flange plates (welded to beam 1, bolted to beam 2, ie no insitu welding needed).
We try not to detail 203 UC due to weight issues, builder will end up splicing which creates it's own set of problems.
Asking a domestic builder to predeflect is not ideal, results will vary!!

1/4 point restraints (welded to beam 1 and bolted to beam 2)

Submitted 5 years 5 months ago

id be most grateful if you can confirm these plates are at 1/4 points only and adequate as restraints in the structural design check???

Engineering by an engineer

Submitted 5 years 7 months ago

As from July 2014 all structural steel need to be engineered by an engineer, The engineer is responsible for specifying the Execution Class for the structure (the works as a whole), and for components and details where it is appropriate to specify an Execution Class different to that specified for the structure. Where different, the Execution Class for a component or detail should not be lower than that specified for the works as a whole. The Execution Class for a component or detail should be clearly identified in the execution specification if it is different to the Execution Class for the structure.

All fabricated steelwork should be completed by a ce-marking fabricator.

Add new comment

CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.

Sign up to the building bulletin newsletter

Over 48,000 construction professionals have already signed up for the LABC Building Bulletin.

Join them and receive useful tips, practical technical information and industry news by email once every 6 weeks.

Subscribe to the Building Bulletin